blob: 76d337da2c4ad75b52f3f09df01bd5c15039152b [file] [log] [blame]
<?xml version="1.0" encoding="UTF-8"?>
<org.eclipse.epf.uma:ContentDescription xmi:version="2.0"
xmlns:xmi="http://www.omg.org/XMI" xmlns:org.eclipse.epf.uma="http://www.eclipse.org/epf/uma/1.0.5/uma.ecore"
xmlns:rmc="http://www.ibm.com/rmc" rmc:version="7.5.0" xmlns:epf="http://www.eclipse.org/epf"
epf:version="1.5.0" xmi:id="-Cn1EflOAHbfuEjRZeLMyzA"
name="new_guideline,_FekBAC4IEdyhZrtGEIITGQ" guid="-Cn1EflOAHbfuEjRZeLMyzA" changeDate="2008-06-30T10:21:13.594-0700"
version="7.2.0">
<mainDescription>&lt;h3>&#xD;
Practice&#xD;
&lt;/h3>&#xD;
An iteration assessment is a short meeting (up to 4 hours) involving the team and stakeholders.&amp;nbsp;The solution&#xD;
increment is used as the focal point for brainstorming, and&amp;nbsp;for considering what functionality might be added in the next&#xD;
Iteration. It is a low ceremony meeting, so the team should not waste too much time preparing the demo and formal&#xD;
presentations. Preparations can, instead, be focused on making the demo fast-paced, and thinking about a good story to&#xD;
present the scenarios planned for the demo [&lt;a class=&quot;elementLinkWithUserText&quot; href=&quot;./../../../core.tech.common.base/guidances/supportingmaterials/references.tech_6CCF393.html#STZ07&quot; guid=&quot;_9ToeIB83Edqsvps02rpOOg&quot;>STZ07&lt;/a>].&lt;br />&#xD;
&lt;br />&#xD;
The team should start the meeting by reviewing the iteration goal before presenting&amp;nbsp;the functionality. The demo should&#xD;
be kept at a business-oriented level, leaving out the technical details. It should be focused on what was&#xD;
accomplished&amp;nbsp;rather than how it was done. If possible, the audience should try to use the product. Minor bug fixes and&#xD;
trivial features should not be demonstrated, but just mentioned, because the audience&amp;nbsp;may lose focus on more important&#xD;
scenarios. Functionality that isn't &lt;span style=&quot;BACKGROUND-COLOR: rgb(255,255,255)&quot;>really completed (acceptance&#xD;
tested)&lt;/span>&amp;nbsp;should not&amp;nbsp;be presented. &lt;br />&#xD;
&lt;br />&#xD;
Team members present the system functionality and answer stakeholders' questions. They also record changes, missing&#xD;
functionality, and&amp;nbsp;ideas for new features in the work item list. At the end of the presentation, the stakeholders are&#xD;
asked for their impressions and the priority of the changes. The potential rearrangement of the &lt;a class=&quot;elementLink&quot; href=&quot;./../../../core.mgmt.slot.base/workproducts/project_work_slot_F12BAC46.html&quot; guid=&quot;_1QZI8EfUEdyiPI8btkmvmw&quot;>[Project Work]&lt;/a> is discussed with the team. Other points of discussion may include:&#xD;
&lt;ul>&#xD;
&lt;li>&#xD;
Were the defined goals and objectives met? Did the release meet its functionality and quality goals? Did the&#xD;
release meet performance and capacity goals?&#xD;
&lt;/li>&#xD;
&lt;li>&#xD;
Were risks reduced or eliminated?&amp;nbsp;Were new risks&amp;nbsp;identified?&#xD;
&lt;/li>&#xD;
&lt;li>&#xD;
Were all planned work items addressed? What was the team's velocity relative to plan?&#xD;
&lt;/li>&#xD;
&lt;li>&#xD;
Did the end-users provide favorable feedback on what was built in this iteration?&#xD;
&lt;/li>&#xD;
&lt;li>&#xD;
Are any changes to the project plan required?&#xD;
&lt;/li>&#xD;
&lt;li>&#xD;
What portion of the current release will be baselined? What portion will need to be reworked?&#xD;
&lt;/li>&#xD;
&lt;li>&#xD;
Have there been external changes (such as changes in the marketplace, in the user community, or in the requirements)&#xD;
that will affect the project plan?&#xD;
&lt;/li>&#xD;
&lt;/ul>&#xD;
&lt;p>&#xD;
Stakeholders and the team may also agree that there is sufficient functionality in the system to provide immediate&#xD;
business value, and they may decide to put the solution into production. In that case, discuss what deployment-related&#xD;
work items should be added to the &lt;a class=&quot;elementLink&quot; href=&quot;./../../../core.mgmt.slot.base/workproducts/project_work_slot_F12BAC46.html&quot; guid=&quot;_1QZI8EfUEdyiPI8btkmvmw&quot;>[Project Work]&lt;/a>.&#xD;
&lt;/p>&#xD;
&lt;h3>&#xD;
Value&#xD;
&lt;/h3>&#xD;
&lt;p>&#xD;
Iteration assessments provide an opportunity for everybody to learn about the solution being built, and obtain vital&#xD;
feedback from stakeholders. It also forces the team to actually finish work and release it.&#xD;
&lt;/p></mainDescription>