| <?xml version="1.0" encoding="UTF-8"?> |
| <org.eclipse.epf.uma:GuidanceDescription xmi:version="2.0" |
| xmlns:xmi="http://www.omg.org/XMI" xmlns:org.eclipse.epf.uma="http://www.eclipse.org/epf/uma/1.0.5/uma.ecore" |
| xmlns:epf="http://www.eclipse.org/epf" epf:version="1.5.0" xmi:id="-KkrHQnR4XqgdNpWEvfFEtw" |
| name=",_zUZ0MPVpEdyJbYuqG3X5Ag" guid="-KkrHQnR4XqgdNpWEvfFEtw" changeDate="2008-08-19T14:32:51.690-0700"> |
| <mainDescription><p>
 |
| The typical Scrum&nbsp;<a class="elementLink" href="./../../../Scrum/workproducts/release_burndown_chart_7E6A4A45.html"
 |
| guid="_tFw9IPVoEdyJbYuqG3X5Ag">Release Burndown Chart</a>shows a single value--the net change in the amount of work
 |
| remaining. In some cases the simplicity of this is wonderful. However, it can also mask what may be going on in a
 |
| project. For example, suppose a team had expected to make progress of 40 (hours, points, whatever) last sprint but the
 |
| burndown chart only shows net progress of 10. Was the team slower than expected or was more work added to the release?
 |
| It's important to know the answer to this question because we cannot really predict when the release will be done
 |
| without it. With this in mind, I've introduced the following type of burndown chart:
 |
| </p>
 |
| <p>
 |
| <img height="300" alt="" src="resources/altrelburndown1.gif" width="400" />
 |
| </p>
 |
| <p>
 |
| On this burndown chart, the height of each bar represents the amount of work remaining in the release. I prefer to
 |
| estimate <a class="elementLink" href="./../../../Scrum/workproducts/product_backlog_68345C16.html"
 |
| guid="_OZIPIOF8Edyp34pwdTOSVQ">Product Backlog</a>, items in "story points" so this figure shows a release with 175
 |
| story points planned in it as of sprint 1. The team finished 25 points in sprint 1, leaving 150 to go as of the start
 |
| of sprint 2. There were 120 as of the start of sprint 3. So, the top of the bar is reduced by the amount of work the
 |
| team finishes in a given sprint. Before the start of sprint 4, the <a class="elementLink"
 |
| href="./../../../Scrum/roles/product_owner_10E7BD3.html" guid="_QcnRMOF5Edyp34pwdTOSVQ">Product Owner</a> added work to
 |
| the project. This additional work is shown at the bottom of the bar for the fourth sprint. You can see that the
 |
| vertical height of sprint 4 goes from about -40 to about 95, or 135 points of work remaining. Fourty of those 135
 |
| points are from new work.
 |
| </p>
 |
| <p>
 |
| Prior to the start of sprint 6 work was removed by the <a class="elementLink"
 |
| href="./../../../Scrum/roles/product_owner_10E7BD3.html" guid="_QcnRMOF5Edyp34pwdTOSVQ">Product Owner</a>. As with an
 |
| increase in scope, a decrease in scope comes off the bottom. This is true whether the work removed is work that was
 |
| initially planned or work that was added during the project.
 |
| </p>
 |
| <p>
 |
| One way to predict how many sprints a project will take is to draw a trend line through the bars and extend the
 |
| baseline. For example:
 |
| </p>
 |
| <p>
 |
| <img height="300" alt="" src="resources/altrelburndown2.gif" width="400" />
 |
| </p>
 |
| <p>
 |
| A problem with this is that predicting the end date as above does not include the rate of change to the scope of the
 |
| project. You can anticipate the number of sprints needed by also drawing a trend line through the changes occurring at
 |
| the bottom of the bars as shown below:
 |
| </p>
 |
| <p>
 |
| <img height="300" alt="" src="resources/altrelburndown3.gif" width="400" />&nbsp;
 |
| </p></mainDescription> |
| </org.eclipse.epf.uma:GuidanceDescription> |