| <?xml version="1.0" encoding="UTF-8"?> |
| <org.eclipse.epf.uma:ProcessDescription xmi:version="2.0" |
| xmlns:xmi="http://www.omg.org/XMI" xmlns:org.eclipse.epf.uma="http://www.eclipse.org/epf/uma/1.0.5/uma.ecore" |
| xmlns:epf="http://www.eclipse.org/epf" epf:version="1.5.0" xmi:id="_mtb-6PL5Edm6Nvont3uinw" |
| guid="_mtb-6PL5Edm6Nvont3uinw" version="1.0.0"> |
| <mainDescription><p>
 |
| This activity is performed throughout the project lifecycle. The goal of this activity is to identify risks and issues
 |
| early enough that they can be mitigated, to establish the goals for the iteration, and to support the development team
 |
| in reaching these goals.
 |
| </p>
 |
| <p>
 |
| The <a class="elementlinkwithusertext" href="./../../openup/roles/project_manager_E657F936.html" guid="_0a0o0MlgEdmt3adZL5Dmdw">project manager</a> and the team launch the iteration. The prioritization of work for a
 |
| given iteration takes place. The project manager, <a class="elementlinkwithusertext" href="./../../openup/roles/stakeholder_9FFD4106.html" guid="_dTa6gMAYEdqX-s4mWhkyqQ">stakeholders</a>, and team members agree on
 |
| what is supposed to be developed during that iteration.
 |
| </p>
 |
| <p>
 |
| Team members sign up for the work items they will develop in that iteration. Each team member breaks down the work
 |
| items into development tasks and estimates the effort. This provides a more accurate estimate of the amount of time
 |
| that will be spent, and of what can be realistically achieved, in a given iteration.
 |
| </p>
 |
| <p>
 |
| As the iteration runs, the team meets regularly to report status of work completed, the work to do next, and issues
 |
| blocking the progress. In some projects, this status checking occurs in daily meetings, which allows for a more precise
 |
| understanding of how the work in an iteration is progressing. As necessary, the team makes corrections to achieve what
 |
| was planned. The overall idea is that risks and issues are identified and managed throughout the iteration, and
 |
| everyone knows the project status in a timely manner.
 |
| </p>
 |
| <p>
 |
| During iteration assessments, the key success criterion is the demonstration that planned functionality has been
 |
| implemented. Lessons learned are captured in order to modify the project or improve the process. If the iteration end
 |
| coincides with the phase end, make sure the objectives for that phase have been met (see <a class="elementLinkWithType" href="./../../openup/guidances/concepts/phase_milestones_5678231E.html" guid="_HNxbwMBJEdqSgKaj2SZBmg">Concept: Phase Milestones</a> for more information).
 |
| </p></mainDescription> |
| </org.eclipse.epf.uma:ProcessDescription> |