<FONT CLASS=indextop> 3.2 endgame build schedule</FONT><BR> <FONT CLASS=indexsub>last
updated April 12, 2006 11:30 EDT</FONT></TD><TD WIDTH="28%"><IMG SRC="http://dev.eclipse.org/images/Idea.jpg" HEIGHT=86 WIDTH=120></TD></TR>
</TABLE><TABLE BORDER=0 CELLSPACING=5 CELLPADDING=2 WIDTH="100%" > <TR> <TD ALIGN=LEFT VALIGN=TOP COLSPAN="2" BGCOLOR="#0080C0"><B><FONT FACE="Arial,Helvetica" COLOR="#FFFFFF">
Schedule</FONT></B></TD></TR></TABLE><P><B>Notes</B><BR><BR>N builds replace tags
specified in org.eclipse.releng map files with HEAD.<BR>I builds use tags in org.eclipse.releng
map files. Teams must update map files in time for I build start times.</P><P>There
will be no rebuilds.<BR><BR>Performance tests will run on all builds that run at 00:10 starting April 12.<BR><BR>Times are all EDT (GMT -5)</P>
<TABLE WIDTH="100%" BORDER="1">
<TR>
<TD COLSPAN="3">&nbsp;</TD>
</TR>
<TR>
<TD ROWSPAN="3"><B>Lead-up to RC1</B></TD>
<TD WIDTH="22%">Mon April 3-Tues April 11</TD>
<TD WIDTH="65%">Daily 00:10 N build<BR> <BR>
Performance baseline at noon, Thursday, April 6th.</TD>
</TR>
<TR>
<TD>Wed April 12</TD>
<TD><p>00:10 N build</p>
<p>I build every 4 hours starting at 8:00 am.</p></TD>
</TR>
<TR>
<TD WIDTH="22%">Thurs April 13</TD>
<TD WIDTH="65%"><P>00:10 I build (RC1 candidate. Ask teams for go/no go on
this build)<BR>
Further builds will be on a request basis only.<BR>
RC1 declared.<BR>
<BR>
Performance baseline at noon.</P></TD>
</TR>
<TR>
<TD COLSPAN="3">&nbsp;</TD>
</TR>
<TR>
<TD ROWSPAN="4" WIDTH="13%"><B>Lead-up to RC2</B></TD>
<TD WIDTH="22%">Friday April 14-Mon April 17</TD>
<TD WIDTH="65%">No builds (Easter holiday)</TD>
</TR>
<TR>
<TD WIDTH="22%">Tues April 18 - Wed April 26</TD>
<TD WIDTH="65%"><p>Daily 00:10 N build<BR>
Performance baseline at noon, Thursday, April 20th.</p></TD>
</TR>
<TR>
<TD>Thurs April 27</TD>
<TD><p>00:10 N build<BR>
I build every 4 hours starting at 8:00 am.</p>
<p>Performance baseline at noon.</p></TD>
</TR>
<TR>
<TD WIDTH="22%">Fri April 28</TD>
<TD WIDTH="65%">00:10 I build (RC2 candidate. Ask teams for go/no go on this
build). <P>Further builds will be on a request basis only</P>
<P> RC2 declared.</P></TD>
</TR>
<TR>
<TD COLSPAN="3">&nbsp;</TD>
</TR>
<TR>
<TD ROWSPAN="5" WIDTH="13%"><B>Lead-up to RC3</B></TD>
<TD WIDTH="22%">Sat April 29, Sun April 30</TD>
<TD WIDTH="65%">No builds.</TD>
</TR>
<TR>
<TD WIDTH="22%">Mon May 1, Tues May 2</TD>
<TD WIDTH="65%">Test pass. No builds. </TD>
</TR>
<TR>
<TD WIDTH="22%">Wed May 3</TD>
<TD WIDTH="65%">00:10 N build</TD>
</TR>
<TR>
<TD>Thurs May 4</TD>
<TD><p>00:10 N build<BR>
I build every 4 hours starting at 8:00 am.</p>
<p>Performance baseline at noon.</p></TD>
</TR>
<TR>
<TD WIDTH="22%">Fri May 5</TD>
<TD WIDTH="65%"><P>00:10 I build (RC3 candidate. Ask teams for go/no go on
this build).</P>
<p>Further builds will be on a request basis only</p>
<P>RC3 declared.</P></TD>
</TR>
<TR>
<TD COLSPAN="3">&nbsp;</TD>
</TR>
<TR>
<TD ROWSPAN="5" WIDTH="13%"><B>Lead-up RC4</B></TD>
<TD WIDTH="22%">Sat May 6, Sun May 7</TD>
<TD WIDTH="65%">No builds.</TD>
</TR>
<TR>
<TD WIDTH="22%">Mon May 8</TD>
<TD WIDTH="65%">Test pass. No builds. </TD>
</TR>
<TR>
<TD WIDTH="22%">Tues May 9-Wed May 10</TD>
<TD WIDTH="65%"><P>Daily 00:10 N build</P></TD>
</TR>
<TR>
<TD>Thurs May 11</TD>
<TD><p>00:10 N build<BR>
I build every 4 hours starting at 8:00 am.</p>
<p>Performance baseline at noon.</p></TD>
</TR>
<TR>
<TD WIDTH="22%">Fri May 12</TD>
<TD WIDTH="65%"><P>00:10 I build (RC4 candidate. Ask teams for go/no go on
this build).</P>
<P>Further builds will be on a request basis only</P>
<P> RC4 declared. </P></TD>
</TR>
<TR>
<TD COLSPAN="3">&nbsp;</TD>
</TR>
<TR>
<TD ROWSPAN="3" WIDTH="13%"><B>Lead-up RC5</B></TD>
<TD WIDTH="22%">Sat May 13, Sun May 14</TD>
<TD WIDTH="65%">No builds.</TD>
</TR>
<TR>
<TD WIDTH="22%">Mon 15-Thurs May 18</TD>
<TD WIDTH="65%"><P>Daily 00:10 N build</P></TD>
</TR>
<TR>
<TD WIDTH="22%">Fri May 19</TD>
<TD WIDTH="65%"><P>00:10 I build (RC5 candidate. Ask teams for go/no go on
this build).</P>
<P>Further builds will be on a request basis only</P>
<P> RC5 declared. </P></TD>
</TR>
<TR>
<TD COLSPAN="3">&nbsp;</TD>
</TR>
<TR>
<TD ROWSPAN="3" WIDTH="13%"><B>Lead-up RC6</B></TD>
<TD WIDTH="22%">Sat May 20, Sun May 21</TD>
<TD WIDTH="65%">No builds.</TD>
</TR>
<TR>
<TD WIDTH="22%">Mon May 22 - Thurs May 25</TD>
<TD WIDTH="65%"><P>Daily 00:10 N build</P></TD>
</TR>
<TR>
<TD WIDTH="22%">Fri May 26</TD>
<TD WIDTH="65%"><P>00:10 I build (RC6 candidate. Ask teams for go/no go on
this build).</P>
<P>Further builds will be on a request basis only</P>
<P> RC6 declared. </P></TD>
</TR>
<TR>
<TD COLSPAN="3">&nbsp;</TD>
</TR>
<TR>
<TD ROWSPAN="3" WIDTH="13%"><B>Lead-up RC7</B></TD>
<TD WIDTH="22%">Sat May 27, Sun May 28</TD>
<TD WIDTH="65%">No builds.</TD>
</TR>
<TR>
<TD WIDTH="22%">Mon May 29- Thurs June 1</TD>
<TD WIDTH="65%"><P>Daily 00:10 N build</P></TD>
</TR>
<TR>
<TD WIDTH="22%">Fri June 2</TD>
<TD WIDTH="65%"><P>00:10 I build (RC7 candidate. Ask teams for go/no go on
this build).</P>
<P>Further builds will be on a request basis only</P>
<P> RC7 declared. </P></TD>