<title>\openup_basic\tasks\assess_results.xmi</title>
</head>
<!-- WARNING: do not modify the generated comments in this file below this line. They are used as markers for the import process. -->
<body>
Element Name: assess_results.xmi<br/><br/>
<!-- END NON-TRANSLATABLE -->
<br/><br/><br/>
<!-- START NON-TRANSLATABLE -->
Attribute: presentationName<br/><br/>
<!-- END NON-TRANSLATABLE -->
<!-- START:presentationName,_0l53cMlgEdmt3adZL5Dmdw CRC: 2553329503 -->Assess Results<!-- END:presentationName,_0l53cMlgEdmt3adZL5Dmdw -->
<br/><br/><br/>
<!-- START NON-TRANSLATABLE -->
Attribute: briefDescription<br/><br/>
<!-- END NON-TRANSLATABLE -->
<!-- START:briefDescription,_0l53cMlgEdmt3adZL5Dmdw CRC: 3775991754 -->Determine success or failure of the iteration. Apply the lessons learned to modify the project or improve the process.<!-- END:briefDescription,_0l53cMlgEdmt3adZL5Dmdw -->
<br/><br/><br/>
<!-- START NON-TRANSLATABLE -->
Attribute: purpose<br/><br/>
<!-- END NON-TRANSLATABLE -->
<!-- START:purpose,_a3uz4LBYEdm7Eph_l9Cn9w CRC: 1759221735 -->Capture and communicate whether the project is on track, requires corrective actions, and whether there are opportunities
for improvement.<br /><!-- END:purpose,_a3uz4LBYEdm7Eph_l9Cn9w -->
<br/><br/><br/>
<!-- START NON-TRANSLATABLE -->
Attribute: name<br/><br/>
<!-- END NON-TRANSLATABLE -->
<!-- START:name,_PABe4MQIEdmaiYJe8-Eaqg CRC: 3624607776 -->Gather stakeholder feedback<!-- END:name,_PABe4MQIEdmaiYJe8-Eaqg -->
<br/><br/><br/>
<!-- START NON-TRANSLATABLE -->
Attribute: sectionDescription<br/><br/>
<!-- END NON-TRANSLATABLE -->
<!-- START:sectionDescription,_PABe4MQIEdmaiYJe8-Eaqg CRC: 1232513160 --><p>
The team should demonstrate the product to customer, end-users, and other <a class="elementLinkWithType" href="./../../openup_basic/roles/stakeholder,_dTa6gMAYEdqX-s4mWhkyqQ.html" guid="_dTa6gMAYEdqX-s4mWhkyqQ">Role: Stakeholder</a>s&nbsp;to collect their feedback, or better yet, have end users to use the product themselves. This
should be done throughout the iteration, or at least in a separate session towards the end of the iteration. Record
requested changes to the product in the <a class="elementLinkWithType" href="./../../openup_basic/workproducts/work_items_list,_rGNWsCbSEdqh1LYUOGRh2A.html" guid="_rGNWsCbSEdqh1LYUOGRh2A">Artifact: Work Items List</a>&nbsp;for later prioritization. Factor&nbsp;the feedback
into the&nbsp;overall iteration assessment.
</p><!-- END:sectionDescription,_PABe4MQIEdmaiYJe8-Eaqg -->
<br/><br/><br/>
<!-- START NON-TRANSLATABLE -->
Attribute: name<br/><br/>
<!-- END NON-TRANSLATABLE -->
<!-- START:name,_o28GgMMsEdmdo9HxCRR_Gw CRC: 1468894915 -->Assess results<!-- END:name,_o28GgMMsEdmdo9HxCRR_Gw -->
<br/><br/><br/>
<!-- START NON-TRANSLATABLE -->
Attribute: sectionDescription<br/><br/>
<!-- END NON-TRANSLATABLE -->
<!-- START:sectionDescription,_o28GgMMsEdmdo9HxCRR_Gw CRC: 2954641234 --><p>
Towards the end of the iteration, the team should jointly assess whether the objectives and evaluation criteria
established in the <a class="elementLinkWithType" href="./../../openup_basic/workproducts/iteration_plan,_0aQBEslgEdmt3adZL5Dmdw.html" guid="_0aQBEslgEdmt3adZL5Dmdw">Artifact: Iteration Plan</a>&nbsp;were met, and whether the team adhered to the
iteration plan and completed all the planned work items. Below&nbsp;are some sample questions that the team can ask
themselves as a part of the assessment:
</p>
<ul>
<li>
<div style="MARGIN-LEFT: 2em; MARGIN-RIGHT: 0px">
Were the defined goals and objectives met? Did the release meet its functionality and quality goals? Did the
release meet performance and capacity goals?
</div>
</li>
<li>
<div style="MARGIN-LEFT: 2em; MARGIN-RIGHT: 0px; LIST-STYLE-TYPE: none">
Were risks reduced or eliminated? Can we identify new risks?
</div>
</li>
<li>
<div style="MARGIN-LEFT: 2em; MARGIN-RIGHT: 0px; LIST-STYLE-TYPE: none">
Were all planned work items addressed? What was the teams velocity relative to plan?
</div>
</li>
<li>
<div style="MARGIN-LEFT: 2em; MARGIN-RIGHT: 0px; LIST-STYLE-TYPE: none">
Did the end users provide favorable feedback on what we built in this iteration?
</div>
</li>
<li>
<div style="MARGIN-LEFT: 2em; MARGIN-RIGHT: 0px; LIST-STYLE-TYPE: none">
Are changes to the project plan required?
</div>
</li>
<li>
<div style="MARGIN-LEFT: 2em; MARGIN-RIGHT: 0px">
What portion of the current release will be baselined? What portion will need to be reworked?
</div>
</li>
<li>
<div style="MARGIN-LEFT: 2em; MARGIN-RIGHT: 0px">
Have there been external changes such as changes in the marketplace, in the user community, or in the
requirements?
</div>
</li>
</ul>
<p dir="ltr">
The assessments should be based on objective measures to the greatest extent possible. For example, to assess that a
given requirement is developed, the team should ensure that the corresponding test cases were successfully run against
it, rather than considering it done when the implementation is done.
</p><!-- END:sectionDescription,_o28GgMMsEdmdo9HxCRR_Gw -->
<br/><br/><br/>
<!-- START NON-TRANSLATABLE -->
Attribute: name<br/><br/>
<!-- END NON-TRANSLATABLE -->
<!-- START:name,_iL7cQEpqEdup0IY9DKDPkg CRC: 1178255518 -->Perform a retrospective<!-- END:name,_iL7cQEpqEdup0IY9DKDPkg -->
<br/><br/><br/>
<!-- START NON-TRANSLATABLE -->
Attribute: sectionDescription<br/><br/>
<!-- END NON-TRANSLATABLE -->
<!-- START:sectionDescription,_iL7cQEpqEdup0IY9DKDPkg CRC: 1583221476 --><p>
Review the approach taken to development and team collaboration, the effectiveness of the development environment, the
suitability of the working environment, and other factors and discuss what things went well, what could have gone
better, and how things could be changed to deliver better results. Capture actions to be taken to improve the
development approach for next iteration in the <a class="elementLink" href="./../../openup_basic/workproducts/status_assessment,_0bA2EMlgEdmt3adZL5Dmdw.html" guid="_0bA2EMlgEdmt3adZL5Dmdw">Status Assessment</a>.
</p><!-- END:sectionDescription,_iL7cQEpqEdup0IY9DKDPkg -->
<br/><br/><br/>
<!-- START NON-TRANSLATABLE -->
Attribute: name<br/><br/>
<!-- END NON-TRANSLATABLE -->
<!-- START:name,_YdoAAM1DEdmLoKw_mVTvhQ CRC: 942688607 -->Refine project scope and duration<!-- END:name,_YdoAAM1DEdmLoKw_mVTvhQ -->
<br/><br/><br/>
<!-- START NON-TRANSLATABLE -->
Attribute: sectionDescription<br/><br/>
<!-- END NON-TRANSLATABLE -->
<!-- START:sectionDescription,_YdoAAM1DEdmLoKw_mVTvhQ CRC: 307789206 --><p>
Depending on the results of the&nbsp;assessment and the stakeholders' feedback, the <a class="elementLinkWithType" href="./../../openup_basic/roles/project_manager,_0a0o0MlgEdmt3adZL5Dmdw.html" guid="_0a0o0MlgEdmt3adZL5Dmdw">Role: Project Manager</a>&nbsp;could need to revise the <a class="elementLinkWithType" href="./../../openup_basic/workproducts/project_plan,_0a6vcMlgEdmt3adZL5Dmdw.html" guid="_0a6vcMlgEdmt3adZL5Dmdw">Artifact: Project Plan</a>&nbsp;to adapt to those changes. If a change affects defined
project milestones, the project manager should consult with the stakeholders before committing to the changes.
</p>
<p>
Necessary changes can also encompass the need to acquire new resources, to absorb an unplanned effort increase, or to
implement a specific change request.
</p><!-- END:sectionDescription,_YdoAAM1DEdmLoKw_mVTvhQ -->
<br/><br/><br/>
<!-- START NON-TRANSLATABLE -->
Attribute: name<br/><br/>
<!-- END NON-TRANSLATABLE -->
<!-- START:name,_wp2CIMMsEdmdo9HxCRR_Gw CRC: 1148511179 -->Close-out phase<!-- END:name,_wp2CIMMsEdmdo9HxCRR_Gw -->
<br/><br/><br/>
<!-- START NON-TRANSLATABLE -->
Attribute: sectionDescription<br/><br/>
<!-- END NON-TRANSLATABLE -->
<!-- START:sectionDescription,_wp2CIMMsEdmdo9HxCRR_Gw CRC: 2323626501 --><p>
This step is optional and must be performed only when the assessment period coincide with the end of a phase.
</p>
<p>
The end of&nbsp;a phase represents a point of synchronization of technical and management expectations and closure for
a project. In iterative development, it coincides&nbsp;with the end of an iteration. However, phase ends mark a point
when it is possible to consider re-scoping and even re-contracting a project. For example, the inception phase is
exploratory and may be appropriately performed under a time-and-materials contract or a cost-plus type of contract. The
elaboration phase could be done as a fixed-price contract or a cost-plus contract, depending on the extent to which the
development is unusual. By the construction and transition phases, enough is known about the system that fixed-price
contracts are more appealing to the acquirer and vendor.
</p>
<p>
The phase end is marked by a major milestone and a corresponding milestone review. The degree of formality of
these&nbsp;reviews depends on the project. The important thing is to take advantage&nbsp;of this milestone review to
achieve agreement among all stakeholders on the current state of the project. For more information, refer to <a class="elementLinkWithType" href="./../../openup_basic/guidances/concepts/milestones,_HNxbwMBJEdqSgKaj2SZBmg.html" guid="_HNxbwMBJEdqSgKaj2SZBmg">Concept: Milestones</a>.
</p><!-- END:sectionDescription,_wp2CIMMsEdmdo9HxCRR_Gw -->
<br/><br/><br/>
<!-- START NON-TRANSLATABLE -->
Attribute: name<br/><br/>
<!-- END NON-TRANSLATABLE -->
<!-- START:name,_1YHH8DLqEdueZPye-FaNgA CRC: 2030100740 -->Close-out project<!-- END:name,_1YHH8DLqEdueZPye-FaNgA -->
<br/><br/><br/>
<!-- START NON-TRANSLATABLE -->
Attribute: sectionDescription<br/><br/>
<!-- END NON-TRANSLATABLE -->
<!-- START:sectionDescription,_1YHH8DLqEdueZPye-FaNgA CRC: 20249945 --><p>
This step is optional and must be performed only when the assessment period coincide with the end of the project.
</p>
<p>
Involve the team and stakeholders in&nbsp;a final assessment for project acceptance which, if successful, marks the
point when the customer accepts ownership of the software product. Gather and record the lessons learned to be used in
future projects. Complete the close-out of the project by disposing of the remaining assets and reassigning the
remaining staff.
</p><!-- END:sectionDescription,_1YHH8DLqEdueZPye-FaNgA -->