<org.eclipse.epf.uma:ContentDescription xmi:version="2.0" xmlns:xmi="http://www.omg.org/XMI" xmlns:org.eclipse.epf.uma="http://www.eclipse.org/epf/uma/1.0.6/uma.ecore" xmlns:epf="http://www.eclipse.org/epf" epf:version="1.5.1" xmlns:rmc="http://www.ibm.com/rmc" rmc:version="7.5.1" xmi:id="-WIgtkwJN71D51FdcQs-TzQ" name=",_nJSDwEvuEdunZcj9T5hrMQ" guid="-WIgtkwJN71D51FdcQs-TzQ" changeDate="2008-09-12T02:38:29.000-0700" version="7.2.0">
<mainDescription>&lt;p>&#xD;
The number of labor units required to complete an activity or other project element. Usually expressed as staff hours,&#xD;
staff days, or staff weeks. Should not be confused with duration.&#xD;