| <org.eclipse.epf.uma:TaskDescription xmi:version="2.0" xmlns:xmi="http://www.omg.org/XMI" xmlns:org.eclipse.epf.uma="http://www.eclipse.org/epf/uma/1.0.3/uma.ecore" epf:version="1.0.0" xmi:id="-YO16TebjP7U0gkcYg7OY_A" name="update_release_plan,{18BF87E6-5849-4091-AFE2-FC4F0C3887B1}" guid="-YO16TebjP7U0gkcYg7OY_A" version="1.0.0"> |
| <sections xmi:id="_oO6dcGE-EdqnIZeW8YpHcA" name="Gather the Information " guid="_oO6dcGE-EdqnIZeW8YpHcA"> |
| <sectionDescription><a id="Step1" name="Step1"></a> |
| <p> |
| The most recent count of completed story points in an iteration is the team's velocity. The number of story points |
| completed in an iteration will change over time. Consequently, the team's velocity also changes. If the team's velocity |
| increases, more work can be done in each iteration. If the team's velocity decreases, less work can be done in each |
| iteration. |
| </p> |
| <p> |
| As the team progresses through the project, the team's understanding of the problem is improved. Customers will add new |
| stories and remove others. Programmers may need to change story estimates. Consequently, the release plan should be |
| revisited periodically (every few iterations or as needed). |
| </p></sectionDescription> |
| </sections> |
| <sections xmi:id="_oO6dcWE-EdqnIZeW8YpHcA" name="Update the Plan " guid="_oO6dcWE-EdqnIZeW8YpHcA"> |
| <sectionDescription><a id="Step2" name="Step2"></a> |
| <p> |
| Using the most recent velocity, the latest story estimates, and the customer's most recent view of priority, a new |
| release plan is established. |
| </p></sectionDescription> |
| </sections> |
| <sections xmi:id="_oO6dcmE-EdqnIZeW8YpHcA" name="Communicate the Plan " guid="_oO6dcmE-EdqnIZeW8YpHcA"> |
| <sectionDescription><a id="Step3" name="Step3"></a> |
| <p> |
| Once the plan is updated, it is critical that the whole team be aware of it. This is usually really easy as the whole |
| team was involved in the revision of the release plan. The plan will show the team the progress they are making |
| (morale), and they will have a clear understanding of the new target they are shooting for (team cohesion).The plan |
| must be realistic and alive. |
| </p></sectionDescription> |
| </sections> |
| <purpose><a id="XE_revise_release_plan__activity_definition" name="XE_revise_release_plan__activity_definition"></a> |
| <ul> |
| <li> |
| Ensure the release plan reflects our improved understanding of the coming releases. |
| </li> |
| </ul></purpose> |