<mainDescription>&lt;p>&#xD;
It's a &lt;a class=&quot;elementLink&quot; href=&quot;./../../../Scrum/guidances/termdefinitions/Burndown%20Chart_F0B781FC.html&quot;&#xD;
guid=&quot;_X5rREILYEduLd8CaF_IcMA&quot;>Burndown Chart&lt;/a>&amp;nbsp;for a given sprint :&amp;nbsp;shows tendency of sprint progress with&#xD;
a graphical representation of the remaining work to do at the end of each passed day.&#xD;
&lt;/p></mainDescription>